North Jetty Improvement Project Phases 2 and 3

Overall site plan for the North Jetty Improvement Project Phases 2 and 3
Scope of Work and Project Improvements
In June 2025, the District completed Phase 1 of the North Jetty Revetment Improvement Project, rebuilding and improving 210 feet of the jetty. The North Jetty Improvement Project – Phase 2 and 3 continues the rehabilitation of the Sebastian Inlet North Jetty structure. Phase 2 and 3 portions of the project entails:
- Installation of 48 pre-stressed concrete piles
- Placement of concrete beams
- Construction of new jetty decking
- Installation of supplemental four-foot diameter granite armor stone and three-foot diameter crib stone
The Project was Bid on July 31, 2026 and August 4, 2026.
Additional information will be available on this site after the project is awarded.
| Bid Task | Dates |
|---|---|
| Bid Advertisement | 7/31/26 (Demandstar) & 8/4/26 (Newspaper) |
| Mandatory Pre-Bid Meeting | 8/14/26 |
| Bid Questions Due | 8/21/26 |
| Bid Opening (Anticipated) | 9/4/26 |
Project Photos
Pre-Construction
A portion of the jetty that will be rehabilitated as part of Phase 2 of the project.
The most recent jetty inspection, conducted in April 2026, recommended major structural repairs.

A view of the north jetty prior to the commencement of Phases 2 and 3.

Point of Contact:
Ed Garland, Public Information Associate
Phone: (321) 724-5175
Email: egarland@sitd.us
