Skip to main content

North Jetty Improvement Project Phases 2 and 3

The image is an overall site plan for a construction project involving a pier with designated phases.
Overall site plan for the North Jetty Improvement Project Phases 2 and 3

Scope of Work and Project Improvements

In June 2025, the District completed Phase 1 of the North Jetty Revetment Improvement Project, rebuilding and improving 210 feet of the jetty. The North Jetty Improvement Project – Phase 2 and 3 continues the rehabilitation of the Sebastian Inlet North Jetty structure.  Phase 2 and 3 portions of the project entails:

  • Installation of 48 pre-stressed concrete piles
  • Placement of concrete beams
  • Construction of new jetty decking
  • Installation of supplemental four-foot diameter granite armor stone and three-foot diameter crib stone 

The Project was Bid on July 31, 2026 and August 4, 2026.

Additional information will be available on this site after the project is awarded. 

Bid Task Dates 
Bid Advertisement 7/31/26 (Demandstar) & 8/4/26 (Newspaper)
Mandatory Pre-Bid Meeting 8/14/26
Bid Questions Due 8/21/26
Bid Opening (Anticipated) 9/4/26

Project Photos

Pre-Construction

 

 

Point of Contact:

Ed Garland, Public Information Associate

Phone: (321) 724-5175

Email: egarland@sitd.us