North Jetty Improvement Project Phases 2 and 3

Overall site plan for the North Jetty Improvement Project Phases 2 and 3
Scope of Work and Project Improvements
In June 2025, the District completed Phase 1 of the North Jetty Revetment Improvement Project, rebuilding and improving 210 feet of the jetty. The North Jetty Improvement Project – Phase 2 and 3 continues the rehabilitation of the Sebastian Inlet North Jetty structure. Phase 2 and 3 portions of the project entails:
- Installation of 48 pre-stressed concrete piles
- Placement of concrete beams
- Construction of new jetty decking
- Installation of supplemental four-foot diameter granite armor stone and three-foot diameter crib stone
The Project was Bid on July 31, 2026 and August 4, 2026.
Additional information will be available on this site after the project is awarded (anticipated on October 14)
| Bid Task | Dates |
|---|---|
| Bid Advertisement | 7/31/26 (Demandstar) & 8/4/26 (Newspaper) (complete) |
| Mandatory Pre-Bid Meeting | 8/14/26 (Complete) |
| Bid Questions Due | 8/21/26 (Complete) |
| Bid Opening (Completed) | 9/4/26 (Complete) |
| Award of bid | 10/14/26 (anticipated) |
| Construction begins | Late 2026/early 2027 |
Project Photos
A portion of the jetty that will be rehabilitated as part of Phase 2 of the project.

The most recent jetty inspection, conducted in April 2026, recommended major structural repairs.

A view of the north jetty prior to the commencement of Phases 2 and 3.
A fisheye lens view looking west from the north jetty.


Point of Contact:
Ed Garland, Public Information Associate
Phone: (321) 724-5175
Email: egarland@sitd.us
Originally posted on August 11, 2026
